The first project over $20 million bid Friday. The renovations to the Clapp Hall portion of the Clapp Langley Crawford complex came in at $25.7 million, which was higher than the DGS allocation for the project. The low bidders were:
Mosites Construction for the general construction. Its bid of $9,801,000 edged out Massaro Corp. by 0.6%.
EMCOR/Scalise was low on both the HVAC at $10,387,000 and the plumbing at $2,246,000. The HVAC budget was reportedly almost $3 million lower.
Kirby Electric was the low electrical bidder at $3,299,000.
Firms looking for the next $20 million project to bid can check out the Fox Chapel High School, bidding on March 5. The project is a $26 million renovation to approximately 300,000 sq. ft. of existing school with a 30,000 sq. ft. addition.