Keeping an Eye on the Big Projects

Bidding activity is very slow as the kids get back to school. The $100 million Section 55A2 piece of the Southern Beltway is out to bid, due Sept. 26. Pitt’s $40 million Salk Hall has been extended again to Sept. 11. The activity after Labor Day will be a good indicator of how the year finishes out. If the pipeline is any indication, there should be a lot to bid in October/November.

Regardless of what projects owners put out after Labor Day, there will be bidding for some of the big projects that have been tracking for the past year or so.

AHN’s new $260 million Wexford hospital broke ground last week and additional bid packages from Massaro/Gilbane should bid through the fall. Likewise, packages for bid on the $190 million UPMC South Hills and $350 million UPMCY Mercy projects will be out. PJ Dick is bidding the 320,000 square foot, $40 million-plus Bakery Square 3.0 office building. CCAC’s new $60 million classroom at the Allegheny campus is expected to be ready to bid in November. The 90,000 square foot building will be bid in five prime packages.

8_web

The Airport Authority’s $1.1 billion Terminal Modernization Program continues to quietly progress. The authority will issue an RFP for construction management services for the project in September, with the expectation of signing a contract in Feb. 2019. An RFP for additional A/E services specific to the $250 million-plus parking garage/lots and ground transportation center will also go out in Sept.

Leave a Reply

Your email address will not be published. Required fields are marked *